The 2021-2022 Enacted New York State Budget established a process for the New York State Department of Taxation and Finance (the Tax Department) to develop a standard appraisal methodology for solar and wind energy systems with a nameplate capacity equal to or greater than one megawatt (MW). The Tax Department, in consultation with the New York State Energy Research and Development Authority (NYSERDA) and the New York State Assessors Association (NYSAA), will annually develop:
- an appraisal Model using the discounted cash flow approach for solar and wind energy systems, and
- corresponding discount rates to be applied for valuation purposes.
Beginning with 2022 assessment rolls, assessors are required to use the model and discount rates to value and place assessments on affected solar and wind energy systems.
Note: Municipalities and school districts will continue to have the flexibility to negotiate payment in lieu of taxes (PILOT) agreements.
This User Guide is designed to assist assessors and stakeholders in entering inputs into and retrieving the appraised value from the 2026 Solar and Wind Appraisal Model (the model) published by the Tax Department. Management and interpretation of the appraisal values are the responsibility of the assessor or stakeholder.
It is the user’s responsibility to enter information specific to their solar or wind project on the Inputs sheet. This is the only sheet in the model that requires the user to enter information.
This sheet contains four sections that allow for user input:
- Inputs for All Project Revenue Types. Includes required and optional user inputs that apply to all projects, color-coded per the “Cover” tab in the model.
- Additional Required Inputs for VDER Projects. Includes required and optional user inputs that apply only to projects receiving Value of Distributed Energy Resources (VDER) revenues.
- Additional Input for NEM Projects. Includes a required user input that applies only to projects receiving Net Energy Metering (NEM) revenues.
- Additional Input for Tier 1 Projects. Includes a required user input that applies only to projects receiving Tier 1 revenues.
Each of the four user input sections is covered in a subsequent section of this guide.
Note: In each section, only cells highlighted in light blue can be modified by the user. After the user selects Project Revenue Type, the model shades the two revenue-specific user input sections that are not applicable for the project. This shading is presented to the user as a black diagonal grid pattern to indicate that these input sections should be ignored.
Figure 1 shows the four user input sections on the Inputs sheet. The shading of the non-applicable revenue-specific user input sections has been omitted for demonstrative purposes.
Required user inputs for all projects are circled in red.
Revenue-specific required user inputs are circled in yellow.
Optional user inputs are circled in blue.
If results do not refresh once input updates are completed, please check whether manual calculations are enabled in the “Calculation Options” section of the “Formulas” tab in the Tax Model Excel workbook. If so, you can refresh the model outputs by selecting the “Calculate Now” option in the “Formulas” tab or by pressing F9 on your keyboard.
Figure 1. User Input Sections of The Model

Interpreting Model Output
The model output (the Present Value of the Cash Flows) is in cell D36 of the Model sheet.
This region of the Model sheet is reproduced below for demonstrative purposes, with cell D36 circled in green. The value in D36 is the sum of the discounted cash flows for the project and reflects the estimated current value of the investment.
Note: All cash flows in the Model are pre-tax.
If a lease amount is entered in the Annual Ground Lease Payment field, then the model output represents the value of the improvements only.
To derive the fair market value of the parcel, the user should use standard appraisal methodology to value the land and add the result to the present value of cash flows.
If the land is not leased (Annual Ground Lease Payment is $0 or blank), then the model output represents the total market value for the improvements and underlying land.
Figure 2. Present Value of Cash Flows Model Output

Note: The model includes a toggle in cell C39 of the Inputs sheet to switch between a presentation of the Present Value of Cash Flows in Nominal Dollars or Real $2025 (“Cash Flow Type.”) As noted in the model, this only impacts the presentation of annual future cash flow values, and will not affect the present value of cash flows. Consistent with prior versions of the model and the practice of using only data available through June 30, 2025, the model assumes that the 2025 discount factor is 1.00 for inflation adjustment purposes, which should be interpreted as a mid-year estimate under a general mid-year discounting assumption. Dollars stated in $2025 should therefore be assumed to reflect inflation through the midpoint of the year 2025.
Inputs for All Project Revenue Types
Project Revenue Type
This required user input determines which revenue(s) the modeled project receives. Due to significant differences between the three Project Revenue Types, this user input has a significant impact on the project’s appraised value. Additionally, this user input determines which of the three revenue-specific user input sections remains unshaded for data entry. The user selects from a drop-down list containing the model’s three Project Revenue Types:
- VDER - Value of Distributed Energy Resources. The New York State Public Service Commission established VDER in 2017 as a new mechanism to compensate energycreated by distributed energy resources (DERs), such as solar and wind. VDER compensates projects in the form of utility bill credits based on when and where (some components vary by utility) they provide electricity to the grid. The amount of compensation is determined by a DER’s energy value, capacity value, environmental value (E-Value), demand reduction value (DRV) and (for a minority of projects) locational system relief value (LSRV). Additionally, certain Community Distributed Generation (CDG) VDER projects may have incentives called the Market Transition Credit (MTC),Community Credit (CC), or Community Adder (CA). These elements recognize thebenefits that DERs provide to the grid and society, including avoided carbon emissions, cost savings to customers and utilities, and other savings from avoided capital investments.1 The model can be used for solar and hybrid solar plus battery VDER projects between 1 MW and 5 MW alternating current (AC) (the maximum project size currently allowed for VDER projects).2
- NEM - Net Energy Metering. NEM projects are CDG projects that were built prior to theimplementation of VDER. These projects receive net metering credits that compensatethem for electricity delivered into the grid based on the residential and commercial retailrate of the local utility. The model can be used for solar NEM projects between 1 MWand 5 MW AC (the maximum project size that was allowed for NEM projects).
- Tier 1. Tier 1 projects produce Tier 1 renewable energy credits (RECs) under New YorkState’s Renewable Energy Standard (RES), which is a mechanism enacted by the CleanEnergy Standard (CES) to help the state reach its clean energy goals and transition toward a low-carbon energy system.3 The RES requires utilities and other load servingentities in the state to procure Tier 1 RECs. Tier 1 RECs are produced by generatorsusing new renewable energy resources that entered commercial operation on or afterJanuary 1, 2015.4 The model can be used for solar, hybrid solar plus battery, and land-based wind Tier 1 projects greater than 5 MW AC. There are not currently any solar orland-based wind Tier 1 projects that are less than or equal to 5 MW AC.
The user should select a Project Revenue Type for their project using the following guidelines:
- If the project is land-based wind, solar, or hybrid solar plus battery greater than 5MW AC, the user should select Tier 1.
- If the project is solar between 1 MW and 5 MW AC, the user should select either VDER - Value of Distributed Energy Resources or NEM - Net Energy Metering.
- If the project is solar plus battery between 1 MW and 5 MW AC, the user should select VDER - Value of Distributed Energy Resources. NEM - Net Energy Metering for solar plus battery is not modeled.
- If unknown, the user can query a publicly available database of solar projects to determine which of these two options to select. Utility interconnection inventories are posted monthly on the Department of Public Service website under the SIR Inventory Information section. If Column AB (Value Stack Y/N) reads Yes or Y, the user should select VDER – Value of Distributed Energy Resources. Otherwise, the user should select NEM – Net Energy Metering.
- If the user cannot find their project in this database, then they should select VDER – Value of Distributed Energy Resources if it commenced operation on or after January 1, 2017, or NEM – Net Energy Metering if it commenced operation before January 1, 2017.
- This input could also be provided by the project developer if they attest to the veracity of the provided information.
The model cannot be used for solar or wind projects smaller than 1 MW AC. For hybrid projects including both a solar and a battery storage component, the solar capacity must be greater than or equal to 1 MW AC, and the battery storage capacity must be larger than 250 kW AC.
Plant Type
This required user input determines the project’s Plant Type. The plant type affects the annual electricity generated by the project as well as various cost data (operating, decommissioning, etc.). The model can be used for four plant types:
- Fixed-tilt solar
- Tracking solar
- Hybrid solar (either fixed-tilt or tracking) plus battery
- Land-based wind
The user selects from a drop-down list that dynamically populates the available plant types based on the currently selected Project Revenue Type. All project revenue types allow for solar, but only the Tier 1 project revenue type also allows for land-based wind.
The user should select Land-Based Wind for all wind projects. The two solar plant types account for whether or not the project’s panels have trackers installed or are mounted to a fixed racking system. Trackers allow the project’s panels to shift their angle throughout the day based on the sun’s position to maximize electricity production, while fixed panels remain tilted in a single, unmovable position. The user should only select Fixed Solar if they have information confirming that the project’s panels do not track, or the project developer attests that the project’s panels do not track.
Hybrid should only be selected if the project includes both solar panels (either fixed-tilt or tracking) and a Battery Energy Storage System (BESS).
System Size
This required user input determines the System Size (also known as nameplate capacity). The system size is used to scale unitized values and affects various cost data (e.g., operating and decommissioning costs). Any system size greater than or equal to 1,000 kilowatts (kW) of AC can be entered into this input.5 The System Size must be entered in kW AC; it is vital that the user ensures that it is entered in the correct units to avoid substantial modeling errors. The electric grid operates in AC, but solar panels and wind turbines produce electricity as direct current (DC). Therefore, inverters are required to convert the produced DC electricity into AC electricity that can be injected into the grid. Due to inverter inefficiency and project-specific design parameters, 1 MW DC of solar panel capacity does not equal 1 MW AC of inverter capacity on the electric grid.
Project developers have the most accurate system size data for their project. If the user can obtain an AC system size value from the project developer, and the developer attests to the veracity of the provided information, then the user should use the value provided by the project developer. If the project developer is unwilling to provide or verify this information, the project’s permitting documents with the local building inspector may list both AC and DC size. Alternately, the user may want to conduct a search for press releases containing an AC system size value for their project. If the user is still unable to determine the project’s system size, they can query a publicly available database of NYSERDA solar projects to find the project’s DC system size.6 The DC system size should then be converted into an AC system size by dividing by 1.34. Note that 1.34 is an approximate AC-to-DC conversion factor, but each project’s actual AC-to-DC conversion factor varies based on its unique design.
Start Date of Plant Operation
This required user input should be set equal to the Start Date of Plant Operation, (the Commercial Operation Date or COD). The Start Date of Plant Operation is used to determine how many operating years the project has remaining before it is decommissioned. It is also used to approximate plant capacity factors for Tier 1 land-based wind, based on NREL assumptions around wind turbine technology types available by installation year in geographic areas specific to NYISO Zones.
The model assumes that all projects have a 25-year operating life. For hybrid solar plus battery projects, the Tax Model assumes that the battery would operate for a 15 year asset life, with the solar operating for the full 25 years.7 The System Age at Taxable Status Date (the value by which the assumed 25-year operating life is reduced) is displayed on the Inputs sheet in cell C9. If a date in 2020 is entered, for example, then the 2026 model reduces the project’s operating life by six years.
Note: Only the year of the date entered is used (entering 1/1/2020 and 12/31/2020 will result in identical appraised values).
The user can find the date to enter via press releases announcing their project’s completion or by querying a publicly available database of NYSERDA solar projects to find their project’s date completed.8 If the project has not yet begun operation, the user should enter the date construction was completed instead.
Entering a date more than 24 years in the past will result in a project valuation of zero, as the project has no operating years remaining.
Tax Load
This required user input should be set equal to the overall full value tax rate for the property where the plant is sited. This rate should reflect all property taxes applicable to the property, including town, county, village, school district, and special district tax rates.
The model allows a Tax Load between 0% and 100% to be entered. The Tax Load is used by the model to calculate the Loaded Nominal Discount Rate, which is shown on the Inputs sheet in cell C13.
To calculate the Tax Load, the user should follow three steps:
- For each taxing jurisdiction, multiply the tax rate per thousand dollars of assessed valuation by the latest final equalization rate (Note: Use the actual equalization rate, not the percentage. For example: 100.0, 90.0, 25.34, etc.).
- Divide the product by 1,000.
- Sum the results of all jurisdictions to arrive at the Tax Load.
For example, assume a project has a town tax rate of 5.561390, a county tax rate of 13.264834, a special district tax rate of 1.024976 and a school tax rate of 29.241161. The total of those tax rates is 49.092361. The property is entirely in one town, so the equalization rate can be applied after the tax rates are summed. The equalization rate is 66. The product of 49.092361 and 66 is 3,240.0958. 3,240.0958 divided by 1,000 equals 3.2401, so the Tax Load to enter into the model is 3.24%.
Annual Ground Lease Payment (if applicable)
This optional user input should be set equal to the Annual Ground Lease Payment amount, if applicable. The entered value will be treated as an annual expense.
If the land is not leased, the user should enter $0 or leave the input blank. As a result of the land not being leased, the model output will represent the total market value for the improvements and necessary supporting land. In the income approach, the land value is inherent to the concluded value, unless removed with a lease expense. For instance, assessors and appraisers may use the income approach to value an apartment building and the land below it.
The land lease information is available from the project developer, who should attest to the veracity of the provided information.
Annual Ground Lease Escalator (if applicable)
This optional user input should be set equal to the escalation rate of the Annual Ground Lease Payment, if applicable. If the annual ground lease includes an escalator clause, the user should enter the escalation rate as a percentage.
If there is no escalator, the user should enter 0% or leave the user input blank for a constant lease. The land lease information is available from the developer, who should attest to the veracity of the provided information.
If the Annual Ground Lease Payment is set to $0 or left blank, then the Annual Ground Lease Escalator input does not have an impact, even if a value is entered.
Additional Required Inputs for VDER Projects
NYISO Zone
This revenue-specific required user input should be set to the NYISO Zone that the user’s project is located within. The New York Independent System Operator (NYISO) runs the state’s electric grid.
NYISO divides the state into eleven main zones for wholesale electricity pricing, which are mapped in Figure 3 below. A dynamic version of this map is also accessible online. The user should use these maps to determine which NYISO Zone their project is in and then select it from the drop-down list.
The model uses the NYISO Zone to determine which energy and capacity price forecasts to use for the project. If a project spans multiple zones, or the user does not have precise location data for their project, they should ask the project developer for the project’s NYISO Zone and have the project developer attest to the veracity of the provided information.
If the project developer is unwilling to provide this information, then the user should make an informed choice based on the user’s examination of the maps.
Figure 3. Map of NYISO Load Zones

Source: NYISO New York Control Area Load Zones9
Utility Company
This revenue-specific required user input should be set to the Utility Company whose service area the project is located in using the drop-down list. The selected Utility Company is used to populate utility-specific DRV data, default maximum MTC/CC data and utility loss adjustment factor data. New York State is served by seven major electric utility companies. The user can query a publicly available database of NYSERDA solar projects to determine their project’s utility company.10 If the user’s project is not in the NYSERDA database, a map of the company’s service area is shown in Figure 4 below. A dynamic version of this map is also accessible online.11 The user should use these maps to determine which Utility Company’s service area their project is located in.
Con Edison (ConEd) appears in the drop-down list four times since it has four different DRV windows. If the user’s project is in ConEd’s service area, they should ask the project developer which DRV window applies to the project and have the project developer attest to the veracity of the provided information. If the developer is unwilling to provide this information, the user should select the 11 A.M. – 3 P.M. DRV window option since it results in the highest project appraisal, all other inputs being equal.
Note: If one of the four ConEd options are selected for the utility company, the NYISO Zone must be set to H – Millwood, I – Dunwoodie, or J – N.Y.C.
If a project spans multiple utility company service areas, or the user does not have precise location data for their project, they should ask the project developer for the project’s utility company and have the project developer attest to the veracity of the provided information. If the project developer is unwilling to provide this information, then the user should make an informed choice based on the user’s examination of the maps and available data.
Figure 4. Map of New York Electric Utility Service Areas

Actual Market Transition or Community Credit or Community Adder/ Inclusive Community Solar Adder
These two revenue-specific optional user inputs allow the user to override the model’s default handling of the incentives known as the Market Transition Credit (MTC), Community Credit (CC), and Community Adder (CA). Certain Community Distributed Generation (CDG) projects receive one of these revenues, but no project can receive more than one of them.
Some VDER projects receive none of these revenues. By default, the model assumes that VDER projects receive the maximum possible MTC/CC for the selected Utility Company, but it allows a lower MTC/CC or a CA to be entered to override this default assumption. The MTC and CC are administered by the utilities and are included in a project’s per-kilowatt-hour compensation. The CA is an upfront lump-sum incentive paid to the project developer by NYSERDA.
The user should ask the project developer whether the project receives an MTC/CC/CA. If so, the developer should be asked to provide the value and attest to its veracity.
If the project developer provides an MTC/CC/CA value or attests that their project receives no MTC/CC/CA, then the user should follow the instructions in Figure 5 to override the model’s default assumption.
If the project developer is unwilling to provide the MTC/CC/CA information, then the user should leave both of these user inputs blank, thereby resorting to the default assumption. The default assumption will lead to the highest appraised value, all other inputs being equal.
The Community Adder input can also contain a value for the Inclusive Community Solar Adder (ICSA). If the project receives a CA but no ICSA, then the Community Adder/ICSA user input should be set to the value of the CA. If the project receives an ICSA but no CA, then the Community Adder/ICSA user input should be set to the value of the ICSA. If the project receives both a CA and an ICSA, then the Community Adder/ICSA user input should be set to the sum of the CA and ICSA. The user should ask the project developer whether the project receives an ICSA. The developer should be asked to provide the value and attest to its veracity.
Figure 5. MTC/CC/CA Model Scenarios
| Scenario | User Enters | Model Behavior |
|---|---|---|
| Scenario 1 | No MTC/ CC/CA Value | If no actual MTC/CC/CA information was provided by the project developer, the model will use the maximum MTC/CC rate for the selected utility company to ensure the highest possible appraised value and incentivize the project developer to provide proof of a lower value if applicable. |
| Scenario 2 | Actual MTC/CC Value | If the project developer attests that their project receives a lower MTC/CC than the maximum default, the user should enter the provided value into the user input cell for the MTC/CC. The model will then use the provided value to override the maximum default assumption. If a project developer attests that their project receives no MTC/CC/CA, the user should enter a value of zero into the user input cell for the MTC/CC to override the maximum default assumption. |
| Scenario 3 | Actual CA Value | If a project developer attests that their project receives a CA, the user should enter it into the user input cell and the model will use the provided value to override the maximum default MTC/CC assumption (which changes to zero since the project can't receive both). CA values are also listed in a NYSERDA database of solar projects.12 |
| Scenario 4 (Invalid) | Actual MTC/CC Value and Actual CA Value | If the user accidentally enters values into both the MTC/CC and CA user input cells, a bold red error message displays warning them that only one of the two inputs can be used (since a project cannot receive both). If the user does not fix this error, the model ignores the entered MTC/CC value and uses only the entered CA value to avoid double counting this revenue category. |
Additional Input for NEM Projects
Utility for Retail Rate
This revenue-specific required user input should be set to the electric utility whose service area the project is located in using the drop-down list.
The selected Utility for Retail Rate determines which residential and commercial retail rate forecasts are used to forecast the value of the project’s net metering credits. New York State is served by seven major electric utilities.
The user can query a publicly available database of NYSERDA solar projects to determine their project’s utility company.13 If the user’s project is not in the NYSERDA database, a map of the utility company service areas is shown previously in Figure 4. The user should use these maps to determine which utility’s service area their project is located in.
If a project spans multiple utility company service areas, or the user does not have precise location data for their project, they should ask the project developer for the project’s electric utility and have the project developer attest to the veracity of the provided information.
If the project developer is unwilling to provide this information, then the user should make an informed choice based on the user’s examination of the maps and available data.
Additional Input for Tier 1 Projects
NYISO Zone
This revenue-specific required user input should be set to the NYISO Zone that the user’s project is located within. This is used to approximate plant capacity factors for Tier 1 land-based wind, based on NREL assumptions around wind turbine technology types available by installation year in geographic areas specific to NYISO Zones.
The NYISO runs the state’s electric grid. NYISO divides the state into eleven main zones for wholesale electricity pricing, which are mapped in Figure 3.
The user should use these maps to determine which NYISO Zone their project is in and then select this Zone from the drop-down list. The model uses the NYISO Zone to determine which energy and capacity price forecasts to use for the project.
If a project spans multiple zones, or the user does not have precise location data for their project, they should ask the project developer for the project’s NYISO Zone and have the project developer attest to the veracity of the provided information. Alternately, the user can query a publicly available database of NYSERDA solar projects to determine their project’s utility company.14
If the project developer is unwilling to provide this information, then the user should make an informed choice based on the user’s examination of the maps and available data.
Renewable Energy Facility Host Community Benefit Program
Under the Accelerated Renewable Energy Growth and Community Benefit Act, certain Large-Scale Renewables, defined as Tier 1 Projects equal to or larger than 25 MW, may be required to contribute to the host community benefit program developed through Public Service Commission Proceeding Case # 20-E-0249. The required payment is an annual fee of $500/MW of nameplate capacity for solar projects and $1,000/MW of nameplate capacity for wind projects, for the first 10 years the facility is operating. Projects that received NYSERDA REC agreements prior to April 3, 2020 will not provide utility bill credits.
Tier 1 Projects required to participate in the program should set the value in cell C36 of the Inputs tab to 1. Projects not required to participate should set this value to 0. This includes projects that have executed voluntary HCAs, PILOTs, or other forms of community benefit agreements outside the scope of the Accelerated Renewable Energy Growth and Community Benefit Act requirement.
Appendix
Overview of E3 RESTORE Revenue Model
RESTORE15 is E3’s price-taker optimization model, designed to evaluate the value of distributed energy resources (DERs) in the transition to a low-carbon, high-renewables grid. It has been utilized to assess both behind-the-meter and front-of-the-meter DER technologies, including storage technologies, in applications such as asset valuation, cost-benefit analyses, market operation simulations, utility retail rate design, and adoption modeling. A diverse set of clients, including utilities, government agencies, developers, and investors have employed RESTORE.
RESTORE is designed to model various storage technologies, such as lithium-ion batteries, pumped hydro, flow batteries, and compressed air energy storage. It is also capable of modeling storage technologies paired with intermittent resources like solar or wind energy. RESTORE stacks customizable revenue streams such as capacity, energy, and ancillary services revenue. RESTORE is employed to estimate the revenue of hybrid solar plus battery systems in the model.
Glossary
| Acronym | Definition |
|---|---|
| AC | Alternating Current |
| CA | Community Adder |
| CC | Community Credit |
| CDG | Community Distributed Generation |
| CES | New York State Clean Energy Standard |
| COD | Commercial Operation Date |
| DC | Direct Current |
| DER | Distributed Energy Resource |
| DPS | Department of Public Service |
| DRV | Demand Reduction Value |
| DPS | Department of Public Service |
| DRV | Demand Reduction Value |
| E-Value | Environmental Value |
| ICSA | Inclusive Community Solar Adder |
| kW | Kilowatt |
| LSRV | Locational System Relief Value |
| Model | 2026 Solar and Wind Appraisal Model |
| MTC | Market Transition Credit |
| MW | Megawatt |
| NEM | Net Energy Metering |
| NYISO | New York Independent System Operator |
| NYSAA | New York State Assessors Association |
| NYSERDA | New York State Energy Research and Development Authority |
| PILOT | Payment in Lieu of Taxes |
| REC | Renewable Energy Credits |
| RES | New York State Renewable Energy Standard |
| Tax Department | New York State Department of Taxation and Finance |
| VDAR | Value of Distributed Energy Resources |
| W | Watt |
1 The Value Stack – Value of Distributed Energy Resources, NYSERDA; 2026.
2 Further discussion on AC is provided in the System Size section on page 6.
3 Clean Energy Standard (CES), NYSERDA; 2026
4 Tier 1 – New Renewables, NYSERDA; 2026
5 System Size can be expressed in watts (W), kilowatts, or megawatts. 1 kW is equal to 1,000 W or 0.001 MW.
6 NEM & VDER Projects: Solar Electric Programs Reported by NYSERDA: Beginning 2000, Open NY; March 4, 2026.
7 National Laboratory of the Rockies 2024 Annual Technology Baseline, Utility-Scale Storage.
8 NEM & VDER Projects: Solar Electric Programs Reported by NYSERDA: Beginning 2000, Open NY; March 4, 2026.
9 A dynamic version of Figure 3 is available online.
10 Solar Electric Programs Reported by NYSERDA: Beginning 2000, Open NY; March 4, 2026
11 A dynamic version of Figure 4 is available online.
12 Solar Electric Programs Reported by NYSERDA: Beginning 2000, Open NY; March 4, 2026 Column AI, Community Adder.
13 Solar Electric Programs Reported by NYSERDA: Beginning 2000, Open NY; March 4, 2026.
14 Large-scale Renewable Projects Reported by NYSERDA: Beginning 2004. Open NY; December 22, 2025.
15 More detailed information on the mechanics underpinning the E3 RESTORE model can be found here.
Tier 1 Projects: Utility-Scale Battery Storage, Open NY; December 22, 2025.